Pre-assembly for the 165-MW Nobelwind project in Belgium is set to commence in June, with work on the 400-MW Rampion project in the UK scheduled to begin in September.
The total space of the MHI Vestas site will expand from 54,200 m2 to 138,200 m2 and will include an extra quay space for the execution of multiple projects simultaneously.
Pre-assembly for the 165-MW Nobelwind project (Belgium) will commence at the site in June, with work beginning on the 400-MW Rampion project (UK) in September.
“We are pleased to be able to partner with the Port of Esbjerg to more than double our footprint on site,” said Bo J. Bjerregaard, Director, Pre-Assembly & Projects, MHI Vestas Offshore Wind, and continues: “Pre-Assembly is a critical aspect of our business and therefore it is essential to have a dedicated site onshore, with the necessary infrastructure where we can prepare our components for offshore installation.”
He added: “This will ensure we can minimize time spent offshore, and thereby reducing installation costs. We are preparing for a busy period where we will execute several projects from Esbjerg and we highly appreciate the infrastructure investment and the flexibility shown by the Port of Esbjerg in supporting our asset light operations.”